Mill and Pave 50 mm (50 mm ACWC)




  1. Area to be repaired is demarcated and confirmed at site with the Engineer representative.
  2. The milling work shall be done as mentioned in 2.3.A.
  3. Subsequently, tack coat (or other surface coating as per scope of works) shall be applied as per specifications.
  4. 50 mm thick of ACWC is then laid and compacted.
  5. Compaction shall follow the rolling pattern established during the trial lay.
  6. The laid material is to be let to cure for minimum of 6 hours and during this duration the lane is to be closed from traffic.