Shoulder Drain (Pre-cast block)


Drain shall be excavated besides road shoulder at 100 mm spacing from the existing guardrail post.  The width and depth shall be as specified in the drawing.  The length of excavation shall be as specified in the bill of quantity.
Gradient of excavation is checked against the requirement.  Upon approval from the Engineer, lean concrete at thickness of 50 mm is laid along the drain. 
The pre-cast blocks are then laid properly as per drawing, ensuring the profile and layout to follow the requirement.