- Area to be repaired is demarcated and confirmed at site with the Engineer representative.
- The milling work shall be done as mentioned in 2.3.A.
- Subsequently, tack coat (or other surface coating as per scope of works) shall be applied as per specifications.
- 50 mm thick of ACWC is then laid and compacted.
- Compaction shall follow the rolling pattern established during the trial lay.
- The laid material is to be let to cure for minimum of 6 hours and during this duration the lane is to be closed from traffic.

Labels:
pavement
Mill and Pave 50 mm (50 mm ACWC)